AQW 3404/22-27 Written question to the Minister for Infrastructure
To ask the Minister for Infrastructure for an update on the cost of the proposed North-South Glider route.
Asked by David Honeyford MLA on 22 September 2022
- Answered
- Written
- Tabled
- 22 September 2022
- Answer due by
- 7 October 2022
- Answered
- 4 October 202212 days after tabling
- Department
- Department for Infrastructure
- Priority question
- No
Answer
The current estimated delivery cost for Belfast Rapid Transit 2 (BRT2) is £142m to £148m, based on the Interim Outline Business Case costings. The estimate is currently being reviewed as part of the finalisation of the Outline Business Case.