AQW 3404/22-27 Written question to the Minister for Infrastructure

To ask the Minister for Infrastructure for an update on the cost of the proposed North-South Glider route.

Asked by David Honeyford MLA on 22 September 2022

  • Answered
  • Written
Tabled
22 September 2022
Answer due by
7 October 2022
Answered
4 October 202212 days after tabling
Department
Department for Infrastructure
Priority question
No

Answer

The current estimated delivery cost for Belfast Rapid Transit 2 (BRT2) is £142m to £148m, based on the Interim Outline Business Case costings. The estimate is currently being reviewed as part of the finalisation of the Outline Business Case.