AQW 10479/22-27 Written question to the Minister for Infrastructure
To ask the Minister for Infrastructure when construction of the B101 North Lisburn Feeder Road from Thaxton, Lisburn, will commence.
Asked by David Honeyford MLA on 19 April 2024
- Answered
- Written
- Tabled
- 19 April 2024
- Answer due by
- 7 May 2024
- Answered
- 7 May 202418 days after tabling
- Department
- Department for Infrastructure
- Priority question
- No
Answer
The North Lisburn Feeder Road, is a developer led scheme.
My officials are working with the developer, the North Lisburn Development Consortium, through an Article 122 Agreement to acquire the final piece of land required to complete the scheme, through the vesting process.
Only when the land is vested, which could take up to a year to complete, can construction begin. I cannot therefore put a definitive time on commencement.