AQW 18183/22-27 Written question to the Minister for Infrastructure
To ask the Minister for Infrastructure for a timeline on the completion of the enhanced park and ride facility at Moira Train Station.
Asked by David Honeyford MLA on 14 November 2024
- Answered
- Written
- Tabled
- 14 November 2024
- Answer due by
- 29 November 2024
- Answered
- 29 November 202415 days after tabling
- Department
- Department for Infrastructure
- Priority question
- No
Answer
In October 2024, my Department issued a letter of offer for £6.6m to Translink to provide 466 new car parking spaces with safe and convenient links to the Moira Train Station. The project will also deliver 23 new disabled parking spaces, along with secure cycle parking, CCTV and lighting. The project is expected start in Spring 2025 and be completed by Summer 2026.