AQW 18183/22-27 Written question to the Minister for Infrastructure

To ask the Minister for Infrastructure for a timeline on the completion of the enhanced park and ride facility at Moira Train Station.

Asked by David Honeyford MLA on 14 November 2024

  • Answered
  • Written
Tabled
14 November 2024
Answer due by
29 November 2024
Answered
29 November 202415 days after tabling
Department
Department for Infrastructure
Priority question
No

Answer

In October 2024, my Department issued a letter of offer for £6.6m to Translink to provide 466 new car parking spaces with safe and convenient links to the Moira Train Station. The project will also deliver 23 new disabled parking spaces, along with secure cycle parking, CCTV and lighting. The project is expected start in Spring 2025 and be completed by Summer 2026.

Official sources