AQW 32065/22-27 Written question to the Minister for Infrastructure
To ask the Minister for Infrastructure for an update on whether any acceptable geotechnical submissions have been received by her Department from the developer's consultants, in relation to the Ayrshire development, Lisburn.
Asked by David Honeyford MLA on 25 September 2025
- Answered
- Written
- Tabled
- 25 September 2025
- Answer due by
- 10 October 2025
- Answered
- 7 October 202512 days after tabling
- Department
- Department for Infrastructure
- Priority question
- No
Answer
I have been advised that the Ayrshire Development in Lisburn has applied for Geotechnical Certification under CD622 Managing Geotechnical Risk of the Design Manual for Roads and Bridges under the title Brokerstown Road.
The developer is currently progressing the various stages required of CD622 and has completed the Statement of Intent and a combined Preliminary Sources Study and Geotechnical Investigation Report stage. Certification of the combined report stage has not been released as the correct geotechnical certificate has not yet been received by my Department.
The Geotechnical Advisor reviewed and commented on the Geotechnical Design Report in April 2025 which is the final phase before construction can commence. Subject to the developer satisfactorily addressing the comments made as a result of this review, geotechnical certification may be deemed acceptable.