AQW 38053/22-27 Written question to the Minister for Infrastructure

To ask the Minister for Infrastructure, pursuant to AQW 5726/22-27, to detail a timescale for the completion of the A1 Junctions Phase 2, between Hillsborough and Loughbrickland.

Asked by David Honeyford MLA on 13 January 2026

  • Answered
  • Written
  • After due date
Tabled
13 January 2026
Answer due by
28 January 2026
Answered
20 February 202638 days after tabling
Department
Department for Infrastructure
Priority question
No

Answer

The A1 Junctions Phase 2 Project will deliver enhanced safety measures along the A1 route, costing in the region of £120 - £130m and will include the closing up of all gaps in the central median and the provision of a number of new grade separated junctions.

The scheme was confirmed by my predecessor as a single package of works on 2 July 2024 and a restricted list was notified to tenderers on 9 May 2025.

Since the judgment on the A5 Western Transport Corridor project and the Department’s appeal, I am taking time to carefully consider the potential impact on other projects as they move through the next stages of their delivery, this includes the A1 Junctions Phase 2 Project.

While we await the ruling from the Court Appeal, my officials continue to work on the next steps in relation to the project and I remain committed to the delivery of this vitally important safety scheme.