AQW 46326/22-27 Written question to the Minister for Infrastructure
To ask the Minister for Infrastructure to detail the timetable for the resurfacing of Main Street, Moira.
Asked by David Honeyford MLA on 15 May 2026
- Answered
- Written
- After due date
- Tabled
- 15 May 2026
- Answer due by
- 2 June 2026
- Answered
- 23 June 202639 days after tabling
- Department
- Department for Infrastructure
- Priority question
- No
Answer
Officials are currently considering the 2026/27 programme of works, details of which will be included in my Department’s 2026/27 annual report to Council. Programmes cannot be finalised until such times as budgets are confirmed.
In the meantime, officials will continue to undertake regular inspections and repair defects in accordance with the Department’s Limited Service policy.